What Actually Caused the Delays in the EU Entry/Exit System Project? eu-LISA has brought legal proceedings against IBM, Atos and Leonardo over delays in developing the EU's Entry/Exit System. I'm looking for documentatio…
두번클릭@twoclicks_later
Delays in the EU entry-exit system must be viewed alongside the readiness schedules at border sites
There is a valid basis for the explanation that the development of the central system was delayed. The European Commission assessed that delays and quality issues with the Entry/Exit System (EES) hindered timely delivery and early acceptance. However, the reasons for delayed delivery and the actual timing of when the system became operational at individual national borders should be viewed separately.
In March 2025, the Commission announced that the start date would be set once the regulations for phased implementation were adopted and the remaining member states declared their readiness. Phased implementation began on October 12, 2025, and full operation started on April 10, 2026. Since there was also a schedule established by the phased implementation regulations, the entire period between these two dates cannot simply be classified as development delay.
Assigning responsibility for development delays requires original delivery deadlines and change records. To understand where and how long the wait times were throughout the overall schedule, I want to compare the dates when individual countries finished field testing and declared readiness alongside the date they accepted the central system.